First year report on the Rooftop Solar Project at AKH Knitting & Dyeing LTD. (Extension Unit)
1. Introduction
2. Project Details
3. Images of The Project
4. Generating Report


5. Project Outcomes
As seen in Figure-2, We can see that the Project has generated over 3.18 GWh worth of electricity. As a result, AKH Knitting & Dyeing Ltd. have saved almost 30 million BDT as revenue from the project.

In Figure-3, we can see the overall generation from July 2022 to June 2023. We can see that the generation was a little low in the winter season but the generation significantly high in the summer. The reason behind the generation gap is mostly because of the low temperature and solar irradiance in the winter season. In the off-peak season, the lowest generation in a month is in the January where the project generated almost 200 thousand Units of electricity. The Highest generation is in the month of May where the project generated over 375 thousand units of electricity.
AKH Knitting & Dyeing Ltd. have also implemented Net metering for their Rooftop solar project. When the load is lower than the solar power generation, the surplus electricity will be fed to the grid. Since AKH Knitting & Dyeing Ltd. have implemented the net metering system, the utility bill will be adjusted according to the amount of electricity they have supplied to the grid. Therefore, there will be no wastage of energy.
Apart from a secondary source of electricity, Rooftop solar projects are being implemented because they reduce the carbon emission and they reduce the use of fossil fuel in day-to-day life. According to Figure-1, the rooftop solar project has saved 1.27 thousand tons of standard coal. For this reason, this project has also reduced 1.51 thousand tons of CO2 emission which is equivalent to planting 2.07 thousand trees.

6. Project Obstacles

7. Conclusion
The Government of Bangladesh is also very enthusiastic about renewable sources of electricity these days. They have also set a goal of 4000MW capacity of electricity generation from renewable sources. Solar EPC Development Ltd. is working to contribute as much as possible to the goal. From all the implemented projects of Solar EPC Development Ltd., they have saved almost 1403 tons of coal, reduced almost 1662 tons of CO2 emission and also generated equivalent energy of planting 2270 trees. The project at AKH Knitting & Dyeing Ltd. is a prime example of the work Solar EPC Development Ltd. have kept on so far. They have almost 10 MW project being implemented as of now and over 50MW rooftop solar projects in their pipeline. Furthermore, they are looking for more and more opportunities to make Bangladesh greener and more efficient.